how much cement is required for 100 sft plastering of ratio
1:4
Answer Posted / ahmed j (if u any question to
Thikness Of Plaster 18 To 20mm
Sand in 1Cubic mtr =1.25 For All Ratio
Cement in 1 Cubic mtr For
1.3 = .21
1.4 = .31
1. Thikness Of Plaster For 1st Coat is Roush Coat 12mm
*Propotion of C:M For 1st Coat With Ratio 1:6 , 1:5,
2. Thikness Of Plaster For 2nd Coat is Fine Coat 6 to 8mm
*Propotion Of C:M For 2nd Coat With Ratio 1:4 , 1:3
Area Is 100sft / 3.28^2 =
9.295 * 0.008=
Area * Thikness
0743*.31=
Volume * Ratio
0.023*1440=
Quantity * Cement Volume
Cement Quantity Required Is 33.20 Kgs (With Out Wastage)
| Is This Answer Correct ? | 35 Yes | 15 No |
Post New Answer View All Answers
What are some structures that may be subjected to fatigue?
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
What is meant by dimensioning?
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
What is the strongest bridge for a school contest?
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)
Use of coping on terrace wall and in 4" wall is compulsory or not ?
in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?
reinforcement slab, beam and column formulas?
in the construction of residential building what type of tank are used?where?why & what is its purpose?
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
Advantage of Aluminum form work in terms of activities can be skip and cost too
What is absolute pressure? How absolute pressure is calculated?
though u r a civil engineer, y r u interested in tcs???