Answer Posted / ahmed j

Thikness of plaster for 1st coat is roush 12mm (1.6)(1.5)(1.4)
Thikness of plaster for 2nd coat is fine 8mm (1.4)(1.3)

Area is 100sft/3.28^2=0.92
.92*.012=0.011

Sand 1cum required is 1.25cum
1.25/4=0.3125

0.01104*.3125*1440=50.19 Kgs Cement

(1.3)

Area = .92mtr sqr *.008(fine)=.0736*0.21=.0156*1440=22.48 Kgs Cement

Is This Answer Correct ?    11 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38

1413


specifications of fe500 steel

3043


what is total volume of ingredients used in concrete accordingly

1806


how find the cut length of tringular ring and any formula find out the quantity of circular brick work

5681


How to decide/consider the grade of bitumen for dbm.

1765






How to plan a project

1717


1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall

1930


How do you calculate reinforcement weight of steel?

666


what is castigliano theaorem

1833


What is the cemnent ratio

1821


Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire

1152


2. What are the advantages of your present job, things you like about it?

2709


cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com

1743


how to calculate the dry wt of sand and cement for a required design mix?for ex:M20

2109


How do You Maintain a structure after getting cube test of low strength.

1825