how many no of cement bags required for 1:4 plastering for
100 sqft?
how many no of cement bags required for 1:3 plastering for
ceiling for 100 sqft?
Answer Posted / ahmed j
Thikness of plaster for 1st coat is roush 12mm (1.6)(1.5)(1.4)
Thikness of plaster for 2nd coat is fine 8mm (1.4)(1.3)
Area is 100sft/3.28^2=0.92
.92*.012=0.011
Sand 1cum required is 1.25cum
1.25/4=0.3125
0.01104*.3125*1440=50.19 Kgs Cement
(1.3)
Area = .92mtr sqr *.008(fine)=.0736*0.21=.0156*1440=22.48 Kgs Cement
| Is This Answer Correct ? | 11 Yes | 6 No |
Post New Answer View All Answers
(Project Management Topic) What are the important criteria in the successful realization of the project?
importance of the soundness test to determine the quality of cement use for any construction
How do you determine specific gravity of cement?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
one steel fixers how much ton steel fabrication he will do same how much tone he will binding?
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?
percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters
To pcc 11 ft x 24 ft .How many bags of cement, sand and aggregate required? And for roofing how many cgi sheets required?
What is proportion of PCC Grade G?
how to calculate the size of triangular ring in rcc column?
Explain moment of inertia?
How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?