how many no of cement bags required for 1:4 plastering for
100 sqft?
how many no of cement bags required for 1:3 plastering for
ceiling for 100 sqft?
Answer Posted / ahmed j
Thikness of plaster for 1st coat is roush 12mm (1.6)(1.5)(1.4)
Thikness of plaster for 2nd coat is fine 8mm (1.4)(1.3)
Area is 100sft/3.28^2=0.92
.92*.012=0.011
Sand 1cum required is 1.25cum
1.25/4=0.3125
0.01104*.3125*1440=50.19 Kgs Cement
(1.3)
Area = .92mtr sqr *.008(fine)=.0736*0.21=.0156*1440=22.48 Kgs Cement
Is This Answer Correct ? | 11 Yes | 6 No |
Post New Answer View All Answers
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
specifications of fe500 steel
what is total volume of ingredients used in concrete accordingly
how find the cut length of tringular ring and any formula find out the quantity of circular brick work
How to decide/consider the grade of bitumen for dbm.
How to plan a project
1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall
How do you calculate reinforcement weight of steel?
what is castigliano theaorem
What is the cemnent ratio
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
2. What are the advantages of your present job, things you like about it?
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
How do You Maintain a structure after getting cube test of low strength.