what is the quantity of formwork in shuttering and
barbending is done by 1 mason and 1 helper
Answer Posted / rajesh n s
Shuttering/Formwork Workdone by 1 Carpenter + 1 helper is 5 to 7 Sqm / day
Barbending by 1 Barnender + 1 Helper is 80 to 100 kg / day
| Is This Answer Correct ? | 37 Yes | 5 No |
Post New Answer View All Answers
Define angular dimension?
What is the worlds largest concrete dam?
cement required for construction of 400mm*200mm*200mm concrete solid blocks for 1sq.mtrs,how?
Test procedure of fly ash bricks as per code ?
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
What is a hatch patterns?
Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)
CAST EFFECTIVE WATER SUMP CONSTRUCTION DETAIL
Bearing capacity of soil determined as per ASTM is to design the foundation size.what is the importance of EV1/EV2 value as per DIN .My consultant ask me to test the the soil as per din to find out this ratio to assess the compacted strength of soil ,,?? is it meaning full ??
what is the cost of rcc roof casting of 400 sq. ft. in kolkata
Form where IS456 is adopted in 1978?
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
Slab quantity
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
In few lines, please be elaborative on extras and talents that make you a potential candidate for the post: