what is the quantity of formwork in shuttering and
barbending is done by 1 mason and 1 helper
Answer Posted / rajesh n s
Shuttering/Formwork Workdone by 1 Carpenter + 1 helper is 5 to 7 Sqm / day
Barbending by 1 Barnender + 1 Helper is 80 to 100 kg / day
| Is This Answer Correct ? | 37 Yes | 5 No |
Post New Answer View All Answers
what is the name of shuttering oil used in oman
Why should you consider yourself fit to be hired by jindal steel.
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
What does civil engineering mean?
What are the alternate material for steel, Sand and aggregate
What is demising walls?
why do we provide haunches in rcc box or underpasses?
what is mc arther pile?
Define current ucs?
how to workable concrete cube test M-25 design mix
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
mix design procedure for 1:6 cement mortar
what is the formula for Mass of cement grout (Dg)=???
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
What is the difference between Fe 500, Fe 500 D and Fe 515.