what is the quantity of formwork in shuttering and
barbending is done by 1 mason and 1 helper
Answer Posted / kamal mukherjee
Is the question technically correct ? General terminology of shuttering workmen is carpenter and steel fixer ins bar bender .
Again the output is linked to the type of the structure in execution.
Broadly Classified as : Sub structure or Super structure
Detailed Classification: Footing, Raft , Column, beam , slab , decorative work: Cantilever, loft, projection works etc..
general working is 2.5-3 sqm of shuttering and 700-750kgs for bar bending works for a pair of workmen
| Is This Answer Correct ? | 8 Yes | 7 No |
Post New Answer View All Answers
undistributed samples are obtained by
sir how can we find the cement and sand required for making 4" drop
cement required for construction of 400mm*200mm*200mm concrete solid blocks for 1sq.mtrs,how?
a butt weld is specified by
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same
What is rate of concrete surface rendering work per sqm
Bernaullis theorem deals with the law of conservation of mass momentum energy none
what is the soil bearing capacity for a 5 floor multistorey residential building and which type of soil ? what is plinth beam? in wall load calculation center to center column distance is considered or not/
can we compare the combined core of DBM and BC density with average density of Lab DBM and Lab BC density
What is the density of 1:1.5 (Cement:sand) ratio in plaster? And Conversion in 12.5 mm thickness per square meter? Howmany Kg of Cement square meter in ratio of 1:1.5?
How should we design a brick column and footing?(note: no reiforcement to be provided) Can you tell me any reference book where i could possibly find this design? Plz help urgently
Which are the Steel tests ?
What year was the keystone power plant in Indiana County constructed?
How to calculate quantity of plum masonry in 1:3:7
why the openings of sieves are square io size?