how to do rate analysis for P.C.C 1:4:8 for 2.83cum(100cft)

Answer Posted / ganesh

Rate analysis is only for Cum
so find outthe material requirment first, and do calculate
as per CPW data
For Ex pls find the below statement,
"Providing and laying in position cement concrete of
specified grade excluding the cost of centring and
shuttering -
-All work upto plinth level: 1:11/2:3 ( 1 Cement: 11/2
coarse sand : 3 graded stone aggregate 20 mm nominal size)"


Sl No Description Unite Quantity Rate
Amount
1 Stone aggregate 20mm cum 0.85 1060.07
901.06
2 Coarse sand cum 0.45 1590.11 715.55
3 Cement bag(50kg) 8 305.00 2440.00
4 Mason Day 0.1 450.00 45.00
5 M/C Day 1.63 300.00 489.00
6 F/C Day 0.7 200.00 140.00
7 Mixer Day 0.07 1800.00 126.00
8 Vibrator Day 0.07 600.00 42.00
9 Sundries LS 14.3 1.00 14.30
10 Total 4912.91
11 Add 1% for Water Charges
49.13
12 Shuttering sqm 3 135.00 405.00
13 Total 5367.04
14 10 % for contractor’s profit and overheads Cost of
1 cum 536.70
15 Total 5903.74

Is This Answer Correct ?    24 Yes 15 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what s the standrd size of pvc fittings ,like elbow, bend,tee etc ? please explain with figure ?

2028


What are advancements in civil engineering?

645


How can we make a hole in a solid rectangle using solidsworks?

760


how many tonnes equals to one cubic feet?

1190


List out some of the common problems that architect have to tackle it?

634






beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?

1652


Dear Sir I Mahesh C. Bhamre have already given a Exam for Superintendent Officer / Public relation Officer Exam Dharmday Aaukta held at Nashik on Date 29/08/2010. My seat no was 5040247. and my cell no is 9822677994. and my mail Id is - mahesh.bhamre@rediffmail.com So can you pl send me details of result of respective exams. Thanking you in Anticipation.

1824


how to caliculate required amount of cement and sand required for 1cu.m.

1735


What is missing report and how to prepare

1022


How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel

1385


Dear Sir What is the Contraction joint for base Slab

1651


how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2

1437


how many litres of enamel paint required for 5000 sft of site?? 

1478


How to calculate carrying capacity of the existing water supply trunkmain

1803


HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?

1748