how much cement is required for 100 sft plastering of ratio
1:4
Answer Posted / shailesh srivastava
6mm thk far 1 sqm
Qty executed=1x1x.006
20% extra for voids & wastage=.0012
total =.0072
30% extra for dry =.00216
Total required qty =.00936 cum
Cement =.00936/5
=.001872 cum
far 1 sqft =.001872/10.76
far 100 sqft =100*.001872/10.76cum
=100*1440*.001872/10.76
=25.052 kg
Is This Answer Correct ? | 9 Yes | 19 No |
Post New Answer View All Answers
how much required strength of cement concrete bricks(size 230x115x75mm)
What is limit state method and working stress method and ultimate method
what is c4x light weight cement blocks
What is bmc stands for in bmc software?
How to calculate quantity of plum masonry in 1:3:7
What is the method of soil replacement test?
how much cement and sand required for 100sqm of wall plastering in different proportions
How do you calculate load bearing capacity of a waffle slab?
How to do base isolation for RC framed structure using ETABS software?
What is the use of array command?
What are moment of inertia and its importance in civil engineering?
can i make bricks using M10 grade concrete ? and what would be the cost of a brick if we use m10 grade concrete sand and aggregates ??
Define What are the materials used in building a gravity dam?
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals