a)If column dimensions are 250*400mm , what will be
cutting length for 8mm stirrups and how to calculate it? b)
If beam dimensions are 200*400mm , beam coveris 25mm , slab
cover is 20mm , what will be the cutting length for
stirrups? c)Column dimensions are 250*400mm , reinf. is
12nos. bar of 16mm dia , stirrups provided are two legged,
what will be the length of each ring?
Regards
Answer Posted / prem chand
A)CUTTING LENGTH FOR 8mm Strips=2*((250-50)+(400-50))+2*
(10*8)- 5*8
=1220mm
clear cover taken as (25+25)mm all around , deduction for
increment lenght (dia x no of bent) ,here dia is 8mm and no
of bent is 5nos.
Is This Answer Correct ? | 8 Yes | 10 No |
Post New Answer View All Answers
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
Define different types of roof systems?
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.
Explain major differences between routing maintenance and major maintenance.
can any one explain bar bending schedule of bems and columns and slabs ??
how much cement and sand required for 1cum rr masonry
What is command line?
very simple or less time consuming formula for reinforcement calculation by moment
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
What is the use of mirror command?
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
why building got air crack? if it get in one particular are what is means?
If we don't have drawing for Excavation of building,At what rule we will go for excavation and how much depth will go for a villa?