The purpose of the Initiation process is to: A. Formally recognize the existence of a project or project phase B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technological advances, or legal requirements C. Formally recognize the stakeholders of the project and identify them in the project charter D. Formally recognize the project sponsor and document his or her project goals
You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail score for the option of opening two new stores in a foreign country. You know, but have not yet informed your company, that you are going to go to work for the competitor, which happens to be bidding for this same opportunity. What is the most appropriate response? A. You decline to participate in the initial meetings with the foreign business partners due to conflict of interest. B. You've not yet received an official offer from the competing company for your new job opportunity, so you choose to participate in the initial meetings with the foreign business partners. C. You decide to participate in the initial meetings with the foreign business partners because any information you gain now will help you when you make the move to the new company. D. You inform the foreign business partners that you're going to be working with a new company and that you know the deal they'll receive from the competing company is better than the one this company is proposing.
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
Sally is a project manager working on the Resource Planning process. She should consider all of the following when developing the resource requirements output except: A. WBS B. Supply purchase policies C. Resource rates D. Special knowledge and talents
During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.
Explain on the project management life cycle process?
Your project has recently experienced change. Some of the agreed-upon WBS elements have been changed as a result. What kind of change has occurred? A. Schedule change B. Risk response change C. Quality change D. Scope change
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
Project managers have the highest level of authority and the most power in which type of organizational structure? A. Projectized B. Strong matrix C. Functional D. Balanced matrix
You are an international project manager from the United States living in a foreign country. The project you're working on has lasted two-and-a-half years. During that time, you've really gotten to feel comfortable in the foreign country and have enjoyed living in their culture. The project has just ended, and you've returned to the United States. Upon your return, you're surprised to find that you're feeling a little disoriented as you've gotten so used to the foreign culture and its slower pace that you've forgotten what some things are like in the US. This experience is known as: A. Diversity shock B. Global norming C. Culture shock D. Culture norming
You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true? A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline. B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against. C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against. D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.
You work for a large manufacturing plant. You're in the Initiation process of a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions should the project manager take? A. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend the project proceed. B. The project manager should document the project's goals and known deliverables in a high-level overview document and assume the project is a go. C. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend a feasibility study be performed. D. The project manager should document the project's goals and known deliverables in a high-level overview document and deliver it to the stakeholders.
You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of Scope Definition. You know if you don't correct this, one of the following could happen: A. The stakeholders will require overtime from the project team to keep the project on schedule. B. The WBS will adversely affect the deliverable breakdowns, and costs will increase. C. The scope management plan will require changes. D. The project costs could increase, there might be rework, and schedule delays may result.
Which of the following project-scheduling techniques allows for conditional and probabilistic treatment? A. GERT B. CPM C. PERT D. CPM and PERT