how much cement is required for 100 sft plastering of ratio
1:4
Answer Posted / karthikeyan.n
1 sq.m = 10.76 sq.ft.
100 sq.ft = 9.29 sq.m
cement required for 10 sq.m = 3/(1+4)=.6*1440/50 = 17.28bag,
100sq.ft cement required = 1.728*9.29 = 16.05 bags
| Is This Answer Correct ? | 34 Yes | 93 No |
Post New Answer View All Answers
What does civil engineering mean?
What is labor and material payment bond?
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
Would you cause a 55-gallon drum of water to weigh more by climbing in?
how to calculate the length diamond shaped striupps in column
How does a traffic light signal work ?
why are you joining in this (applied post) job and your aim for this job
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
Moisture content calculation for diff mix ratio's ??
detailed calculation of the amount of cement used?
What is structural frames or systems?
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
Different sizes of Hollow blocks and its weight. Thanks.
What is fineness modulus ? and its sieve # ?