Answer Posted / rohit garg
For a power plant Maximum Demand is a important factor for
deciding its billing and the requirement of power from the
electricity board. It is defined as the peak demand of
power whenever the maximum load is there in operation or in
running process in the plant for the particular time period.
Maximum Demand is used to decide contract demand too and it
is generally kept at 75-80% of contract demand. If demand
of plant exceeds maximum demand limit at any time there
will be penalty for that.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
how you configure motorvision relay (L&T make)from DCS
Difference between rating factor of cable and derating factor of cable?
i have applied for junior engineer 2 c&w for Guwahati RRB please send me last five year question paper
How does an oscillator differ from an amplifier?
what is the diference between the 4pole & 6pole DC Motors & what is advantage 6pole over the 4pole ?
how to control dc motor?
what is the maximum temperature rating of a thhn insulated conductor?
What is difference between start imitation and start interlock for 3 phase motor protection ?
How will polarity test of Dy5 Transformer ?
WHY THE DIMENSION OF TWO SAME RATED MACHINE IS DIFFERENT ?
what is meant by directional earth fault and non directional earth fault? describe both.
Please sent me some previous year question papers of BSNL-JTO telecom and RRB in ELectrical Engineering to varshashahi@yahoo.com
What will happen if we on 200kvr capacitor bank(11kv in bus)If there is low load on transformer (1.5 mva 33/11 kv)
In the formula : Knee point voltage = Burden X alf / class, Please inform what is alf? regards Shashidhar M.R.
How to calculate the Harmonics losses in terms of cost/unit.