how much quantity of work we can get by rod benders per day
Answer Posted / sunil
as per my experience..in building..rod bendender do do
quantity...only 3 tons(the steel only less and small dia)
in bridges.1.5- 2 tonn( in slabs and abutments )
including binding also
| Is This Answer Correct ? | 0 Yes | 14 No |
Post New Answer View All Answers
what is the 0 value in quantity surveying
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
what values & beliefs have guided you in your career path
Mention different types of roof systems?
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
what is the formula to find the sttel (bar)length in beam having bent up at l/4 t 45 degree & 60 degree.
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
what is grade intersection?
How do you compute the volume of airflow?
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
Define What is unit weight of normal concrete?
Types of column foundation and how to calculate its steel quantity.
Why should pumping be not used in case of concreting work?
Define What is the difference between routing maintenance and major maintenance in school facilities?