As per thumb rule cement required per 1 cum of M20 concrete
is 411Kg/cum(1.57/5.5=0.285cum of cement i.e
0.285*1440=411Kg).But as per PWD rate analysis cement
required is 347Kg/cum.the difference is 64Kg.This kind of
difference is coming every grade of concrete.Can you give
perfect suggestion regarding this.
Answer Posted / karan sardana
this is because you are using design mix instaed of nominal.. the qty of cement in 1 cum of concrete is 411kg, but in design mix the cement consumption is considerably reduced, thats why you are getting this difference always.....
| Is This Answer Correct ? | 22 Yes | 2 No |
Post New Answer View All Answers
Laying bitumen concrete 40mm thick using 0.1372 cum of 13.2 10mm metal ,0.2387 cum of 10 5mm metal...what did it means please explain me how much cum of 10 mm metal need?
Can we use the flyash bricks in brick bat coba?
How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight
What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?
which method is used in semi-rigid connection design??
What is the biggest dam in america?
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
States some of the tool bars used in cad?
How do you maintain water pressure?
Explain what are the phases inspections are done by local authority while construction?
A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L
Pls explain me about tension and compression in a flat slab
Would you cause a 55-gallon drum of water to weigh more by climbing in?
What is the software used in civil engineering?
How to plan a project