Answer Posted / pavan kumar
hi everybody,
as per terms of payment and base line date the no.of due
days will be calculated ...here iam adding one point to
this statemnt is
baseline line date can be either entry date or posting date
or doc.date .... u need to do these settings in the place
where u define ur payment terms...
and while u r seeing in any report u c the no.of due days
as arrears(in SAP terminology)
thank u....
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How are scrap costs shows in the standard cost estimate?
What are document types and what are they used for?
What is the purpose of "document type" in sap?
Explain open sql vs native sql?
Is it possible to calculate standard cost estimate for a past date?
What is a payment block? : fi- accounts payable
What is Unit Testing & Integration Testing. Explain with example considering FICO module.
Explain cost center accounting? : co- general controlling
How do you ensure correct balances in the financial statement? : fi- general ledger master data
in which server did number ranges of CO mainly created? is it in development server or in production server? Plz. give the reason.
How are tolerances for invoice verification defined?
What are the problems faced when a business area is configured?
How to FI integrate with MM and SD.
What are fi validation rules?
What does field status group assign to a gl master record controls?