Answer Posted / ashwin sonwane
when the length of bar available in market is smaller or
when the pieces of bars are to be utilized the bars are
required to be lapped
a) flexural tension: Ld or 30dia,whichever greater
b) direct tension: 2Ld or 30dia, greater
c) compression:Ld or 24dia, greater
straight length of lap should not be less than 15dia or 200
mm, minimum
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9
step by step procedure to find out the percentage of steel in coloum,beam,slab,footing in detailed
what is the types of surveying?which type of survey carrying for type of work?
how many monpower required for 1 sqm normal RCC structure ( includes finishes & MEP )
rate analysis for cement pointing 1:4 , for 100 sq m
How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What is thumb rule in quantity and cost estimation of a residential building?
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
what is the use of water bar in water tank and is this an extra item in estimate?
What are new methods /technologies of pothole patching?
explain fie benefits of using standard terminology in the measurement process
find the discharge of water through a horizental venturimeter having 400mm dia at the inlet main and 150mm dia at thorat.if the diffrential gauge between inlet and thorat shows a pressure head of 25cm mercury. assume coefficient discharge 0.98 and specfic gravity of mercury as 13.6.
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
How is the strength of cement measured?