there is a line fault some where on the ove head
distribution line. how will i locate the fault for clearing
it? ofcourse i have to megger the line but what information
makes me clear that the fault is in that section of the
line?
Answer Posted / aamod tripathi.
The fault if is in a over head distribution line it is
generally taken care by the protection system (Relays/
CBs)This gives the answer of your question as What
Information makes it clear that the fault is in that section
of line. And as the protection system is quite selective (It
is its important feature while selecting the protection)
Even then if fault occours in Line (Not Cable) The visual
inspection is carried out once the span is known. (Generally
Open Circuit (Breaking of conductor)or short circuit (LG,
LLG,LL fault has occoured due to insulation failure or tree
fallen, or Snake, or Bird)
If it is a cable Megger is the best option to use. The
solution is to join the cable (Not Done Generally) or to
replace it.
For information: THE CABLE IS THUS REQUIRED TO FACE THE
MAXIMUM NUMBER OF TESTS AFTER MANUFACTURING. AS WE DONT
INSTALL ANY BACKUP FOR CABLE.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
11 kg trivevter meter has rating of -/5amps. And pt ratio11000/110v and is connected with 11kv ct/pt unit of cr ratio 75/5amps. And pt ratio of 11000/110v while checking accuracy of meter with HT Accuchek meter what value of PT ratio and CT ratio to be filled in Accuchek meter
how the aircraft outer body and inner body is separated ?
advantage and disadvantage of team work?
some basic standard questions on transformer.
what are problems caused by the pdu in rack server
Why the cores of large transformers build up of circular cross section?
Why do we require transformer with less specific weight if supply frequency is increased?
If i have two 3000 kW motors and the whole facility requires a 10 MVA transformer. What would be better installing two 5 MVA transformers(one for 1 motor ) or just a single 10 MVA transformer for both of them. Give reasons for your answer.
sir pls tell me . our ct specifications are 120/5 ,2 core , 0.2 and 5p10 class , 30va and 30va buden. insted of 30 va i want use 15 va. can i use?
acb(AIR CIRCUIT BREAKER)NOT CHARGING AUTO
What current flows in the transformer primary when its secondary is open?
According to IEC60034-14, When the vibration monitoring system required for motor Bearing. above which KW, it is required? and for what type of bearing the vibration probe is provided.
I am getting above 60 V as open delta voltage against single phase unit ICT at tertiary delta formed and ICT getting trippped on NDR. ICT tested and found in order. PTs provided on tertiary are tested and in order. what may be the reason?
What are the types of feedback oscillators?
either water sensor or flow meter,how we observe the water level, f any other equipment are in market ?