Answer Posted / mustafa mohd layeak
Minimum reinforcent in columns = 0.87% of c/sect column
area and a column must atleast have 4 bars, as per IS code
a maximum of 6% is allowed but it is advised to restrict it
at 3 to 4 % due to practical problem of spacing between
bars for concrete placing.
| Is This Answer Correct ? | 14 Yes | 3 No |
Post New Answer View All Answers
what is the difference between replacement of cement by groundnut shell ash
How to do base isolation for RC framed structure using ETABS software?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
undistributed samples are obtained by
In case if concrete box girder bridges how is the number of cells determined?
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
The mixture of different ingredients of cement is burnt at?
How will you Engage Labours on Site?
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
How many litres of water used for curing of 1000sqft of slav
What are the advantages of building a dam on the river nile?
how i convert mm into standard wire guage (SWG)no.
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
Exterior Joints,define
What is the diameter of the 3"inch nails?