1. which type of transformer connection is preferred in
case of power supply transformers?
(A) Star/Star
(B) Delta/Delta
(C) Star/Delta
(D) Zig Zag/Star
2. In a power transformer usuall which winding is closer to
the core?
(A) Primary winding
(B) Secondary winding
(C) Low Voltage winding
(D) High Voltage winding
3. The power factor of a purely inductive load is
(A) Zero
(B) Lagging
(C) Leading
(D) Unity.

Answer Posted / gaurav agarwal

1. star/delta
2. secondary winding

Is This Answer Correct ?    3 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Define open loop control system.

675


any application of back emf

1615


How to calculate cable size by using load.?? Any formula...

898


List of equipments required foe industrial repair lab.

1498


Why temperature rise is conducted in bus bars and isolators?

755






3phase motor can be used as a Prime mover for alternator.

1167


Are Refrigerators & Deep Freezers the Inductive load ? How to calculate the Power Factor & hence the Output Power for them ?

4623


i have 90kw motor.so i choose connect cable .please what is parameter checked so please give to formula

1723


do anyone out there know where to find a compleete list on acronyms/abbreviations used in offshore electric engineering. MCB - Micro Circuit Breaker, MCCB-Mouldes Case Circuit Breaker, ELCB-Earth Lekage Circuit Breaker, ELMCB- etc.....

1556


Why 3 phase induction motor getting supply in body if one of it's phase is cut

1268


Explain M Var? Which types of problem occurs when reactive power increase at the time of full load of plant and at the time of synchronize of plant?

1317


I want to put this query to SENIOR & EXPERIENCED ELECTRICAL ENGINEERS. 1)I want to know about the control circuit diagrams for control panels. I found it difficult to understand. Is there ant booklet through which we can learn the circuit diagrams? 2)I want to learn about conduiting, laying cables, preparing cable schedules and various techniques which is the part of building infrastucture(construction field). I don't have any experience in this area. I have experience in control panels only. that's why i am not getting any opening in building infrastucture (construction field).Can I get the job in this field as Trainee Engineer? How to enter this field? I need job in PUNE

1483


Pl. brief about break-down maintenance of machine tool.

1369


why dc is used in control circuits for MV & LV switchgeras instead of ac

1467


generally in LT and MV motors we are using 3.5Coresx16,25,35,50 etc cable for supply.although motors is earthed at two point and having all protection.then why we are using that 1/2 core for earthing the motors.while in HT cable we are using only 3core cable for motor supply.generally lt and mv motors are delta connected and ht motors having star connection.whethere it is having any relation with winding connection( star or delta).all motors i am talking about are dol only.can anybody solve my confusion.thanks...

1537