i have done changes in an order (delivery date etc) and
save . but when i go to change option in environment
tab ,i found no chnages has been made. kindly revert its
urgent
Answer Posted / pitabash
Hi !
If you change the delivery date only in the header then .it
does not shown you in the Change log, It need to change
the delivery date in the schedule line also . Then it
should shown in Enviornment change log.
Regards
Pitabash
Infosys, pune
Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
customer hierarchy in sap sd for account determination
how to fill the GAPs in BBP?give me one example thanks in advance venkatesh
Define Product attributes?
What two ways of number assignment for documents or master data do you know? Explain the difference between them.
If you generate bill more than credit limit then what will happen?
What is the difference between sd account key and fi account key?
Can you make texts mandatory for a customer master or a sales document?
Sir, I'Ve interview with IBM . I want few SAP-SD real time tickets and its solution .Its urgent. Plz help me . thanks in Advance
How are the sources and targets definitions imported in informatica designer? How to create target definition for flat files?
How does SAP get to know whether the material is available or not? how does it determine MAD? What exactly happens in sending TOR?
What is the Difference between WM and EWM?
What is partial delivery agreement? In which master data is it defined? What are the different types of partial agreements available in sap sd ?
Copying is not possible. because an entry is missing in Table TVCPL: TA TAN Message No. VL473
monitoring Magic Service help desk for issue posted by the end user on daily basis (2) Analy
How do you create sales organisation?