we are small scale industry in production of rice & rice
bran. Pls let me know how to take contract demand for our
industry.. (for information we have total 600.hp)
Answer Posted / sumeet
First of all please estimate your mill load, office load
(lighting load and air conditioner load).
As per you have shown 600 hp load your contract demand will
be 447.6 kW i.e 527 KVA considering 0.85 power factor
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is negative sequence over voltage element?
I had applied for JE in PSEB, Can you pls send me the Question bank for related to my field
what is method for testing CT
how to determine the inrush current of a transformer
In siemens S7-300 PLC, what is function and function block ? What is the difference between them ? When to use function and when to use function block ?
An 8 pole, 50 Hz, 3-phase IM is loaded to a poing where pull out torque will occur. The rotor resistance per phase is 0.3 ohm and motor stalls at 650 rpm. The slip when motor stalls is A 1 B 0 C 13.33% D 10.33%
hi frnz,can somebody give me any project work? i am a 2nd year student & interested in practical works...plz give me some projects
How can i calculate the Breaking capacity of molded case circuit breaker, is the breaking capacity of CB for Diesel generator shall be less than grid supply's breaker ?
What is installed in PAC that is control the humidity
if we have a industrial load of 400 kilowatts with 415 volt AC then how much total harmonic distortion (thd%) should be acceptable for steady power system.
What are the internal and external faults?
why the electrolyte level in lead acid battery is maintained 2.5 cms above electrodes?
Where is servomechanism used?
how does directional relay work incase of ac ?
how give earthing conection to household equipment?