What is the amount of no load current of 630 kVA tranformer
voltage ratio 11kV/440V ?
Answer Posted / dr. alaa baiumy abdel azim &a
frist we will get the rated current of the winding
I = 630 * 1000 / CUBIC ROOT OF 3 * 11 * 1000
I = 33 Amper
I NO LOAD = 0.5% OF I RATED
NO LOAD CURRENT = O.OO5 * 33
= 165 m A
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
why most of junction box vendors providing T5/T6 Temp class jb's for T3 area any special reason?
i need to now what will be the cable size to the following load, transformer to distribution panel distance 110m, load 1000kw, voltage 400v, pf 0.85, permissible voltage drop 2.0%, overhead line, atmospheric temperature 35 degree c.
Y phase plates are used in transmission line??? what is there need???
How the circuit breaker is selected for Induction motor of 100 kW, 415 volt, 0.85 power factor, 0.95 efficiency ?
What is the Good Earth resistance value of G.I & Cu. Chemical Earthing & Normal Pipe Earthing?
What is main cause of cable's terminal point burned in Lug on high temperature although lug and cable selection is ok as per stantard and also tightness is ok as per situation. so please take in deep and tell correct answer thanku.
my UPS suddenly goes off and all panel light also blow off.This happens even main electric supply is not interrupted.After some time it automatically starts functioning normally.Batteries are new.
what is ground fault in ACB?
How to calculate VCB rating for 33KV ,25 MW Power line?
A commercial Building is designed with 14th floor levels with indoor substation of three phase transformer with rated capacity of 1000 Kva.The transformer delivered 65% of its rated capacity at 0.67 power factor lagging.Because of low power factor, the power customer was penalized and certain cost was charged accordingly based on every point percentage lower than 85%.This situation may repeatedly happen on the succeding energy bills of power customer.The power customer is desired to improve its historical power factor of 0.67 lagging and no further penalty be impose by the local power company on the next bill. Q: Identify the appropriate solution you want to offer to Client?.Justify SCIENTIFICALLY and MATHEMATICALLY the principles behind the solution.
Air refrigeration cycle works on the
can u tell me the promotion from oiller to enginer
What is the meaning of loop in transformer
Why we do 2 types of earthing on transformer (ie:)body earthing & neutral earthing , what is function. I am going to install a oo kva transformer & 380 kva dg set what should the earthing value?
Hi,iam a diploma in electrical engineering.rtd from indian air force in apr 2007.prsently working in reliance next link as a network maintenance engineer since 2007,can i get a job in motherson sumi.