If I have 3 different process chains then how can I create
a Metachain including all these 3 local chains ? Step by
Step procedure would be much appreciated as I am going to
try the suggestions provided on system. Thank you.
Answer Posted / ola oladute
Use event-controlled processing to automates all the 3
local chains as follows:
1. Use t-code SM62 to create an Event
2. Go to SM36 to create a job
3. Click on start condition, give the start date and time
of Process Chain no. 1
4. Create the job using program BTC_EVENT_RAISE. In the
variant give the event name as A
5. Include the event A in step 4 in the start condition of
PC (Process Chain) no. 1. Also include a program that will
raise event B
6.Include event B name in the start condition of PC no. 2.
Include a program that will raise event C
7.Include the event C name in the start condition of PC no.
3.
8. Go to SM64 to trigggered the event
| Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
How will you schedule the job in background?
How is ?:? useful as an authorization value?
What is persistence mode in cache?
How will you get more details on data source and delta modes?
Explain ods?
How would you do the archiving cubex.
Give some examples of usage of BW statistics reports?
What are the steps to do the converting from lis to lo extraction.
What is occurence
What exactly do you know about the term data flow in the business intelligence or business warehouse?
What are the inputs for an infoset?
Where do you find which table is currently being populated (BIW1 or BIW2)?
Give an example of it?
What is sap bw/bi? What is the purpose of sap bw/bi?
What is the table filled when you select ABAP?