I've one slab of 24m x 43m. How to calculate required steel
For this slab.
Answer Posted / surajit ghosh
LBD= 24 X 43 X 0.125 (SAY, REQUIRED TO ACHIEVE AS PER
DESIGN)= 129 CUM
VOLUME OF STEEL 1% (SAY, REQUIRED TO ACHIEVE AS PER DESIGN
& BBS)= 1.29 CUM= 1.29X 7850 kG= 10126 kG, Apx= 10 Ton.
| Is This Answer Correct ? | 14 Yes | 6 No |
Post New Answer View All Answers
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order
Define What is the distance between railway tracks?
how to calculate number of bitumen for road asphalt
Why the statue of liberty is made of copper?
how to determine H- zone in a column? where it will occur?
What is soil enforcement?
What is the sugested procedure of water purification for public supply?
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
how to estimate costing from quantity givin in BOQ and according to this how we fill tender and final rate for perticular work.....?
explain the rale of the government in the construction industry
at what pressure ply-wood is obtained by gluing wooden sheets
What are some facts about concrete?
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?