how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / subilash .s(civil engineer)
for designing 1m3 concrete of M25 mix the ratio is 1:1:2
for calculating cement,sand and course aggregate ,
cement= 1/(1+1+2)=.25
density of cement =1440kg/m3
cement required for this mix=1440*.25=360kg=6bags+10kg
sand=1/4=.25m3
course aggregate=1-.5=.5m3
this methode of designing is known as volume batching ,this
methode will be ues to design mixes upto m25.
| Is This Answer Correct ? | 86 Yes | 69 No |
Post New Answer View All Answers
Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice
length where bent up is made in slab of bridge from one end
how we calculate the grade of the Bituminous materials.?????
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
what is the breaking strength of wall tiles
is basic cost of the material includes tax?
Soil bearing capacity formula
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
For Wet Mix Mecadam design what is Optimum moisture content
How to calculate canal slope curvature qty!
how to prepare site mix design
what is the theoritical percentage of concrete cubes testing per day?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.