is there any difference in reading or error in value, if we
connect the R phase in Y terminal and Y phase in R terminal
of electronic energy meter of 11 kv feerders???

Answer Posted / k.prakashchandra

No. But corresponding CTs and PTs should not be
altered.Please note that the R, Y, B phases of one station
may be different from those of another station.In case of 11
KV, only phase sequence is considered. Energy recorded by
energy meter is the sum of individual measuring elements..

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

During underground cabling in landscape area what did we cover the cable with to prevent the electric shock & protect the cable?

1405


HAI SENT HPCL APTITUDE QUESTION PAPER, MY EMAIL ID IS angus_eee04@rediffmail.com,angus_eee04@yahoo.com

1704


what is excitation/

1722


how will we calculate the copper wire load..

1448


How I calculate the ELCB for circuit breakers?

1655






how test transfomer(3 phase75kva) by megger

1611


Draw the DOL starter and star delta starter drawing?

2514


what is the reason the main breaker is trip during the motor is running? (some time the breaker is not trip)

1299


How to calculate approximate load loss of a distribution transformer by knowing %ge imp of transformer?

1742


What is the formulae of Megger value for a A.C.Motor

2288


What is stepper motor. What is its uses?

651


how to changeover ups in this power failur time?

1521


when we have to purchase the transformer by own i.e how much load will preferred HT connection?

1194


why are u join ntpc

1721


what is the preventive maintence for ht panels and busbars and vcb abd acb's.

1852