is there any difference in reading or error in value, if we
connect the R phase in Y terminal and Y phase in R terminal
of electronic energy meter of 11 kv feerders???
Answer Posted / k.prakashchandra
No. But corresponding CTs and PTs should not be
altered.Please note that the R, Y, B phases of one station
may be different from those of another station.In case of 11
KV, only phase sequence is considered. Energy recorded by
energy meter is the sum of individual measuring elements..
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
During underground cabling in landscape area what did we cover the cable with to prevent the electric shock & protect the cable?
HAI SENT HPCL APTITUDE QUESTION PAPER, MY EMAIL ID IS angus_eee04@rediffmail.com,angus_eee04@yahoo.com
what is excitation/
how will we calculate the copper wire load..
How I calculate the ELCB for circuit breakers?
how test transfomer(3 phase75kva) by megger
Draw the DOL starter and star delta starter drawing?
what is the reason the main breaker is trip during the motor is running? (some time the breaker is not trip)
How to calculate approximate load loss of a distribution transformer by knowing %ge imp of transformer?
What is the formulae of Megger value for a A.C.Motor
What is stepper motor. What is its uses?
how to changeover ups in this power failur time?
when we have to purchase the transformer by own i.e how much load will preferred HT connection?
why are u join ntpc
what is the preventive maintence for ht panels and busbars and vcb abd acb's.