how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / sandeepthakur1981
for 01 cu.m.
cement=1.52/7 =.217
= .217x30= 6.51 bags.
sand= .217x2= 0.434cu.m
aggregate= .217x4= 0.868cu.m
Is This Answer Correct ? | 94 Yes | 35 No |
Post New Answer View All Answers
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
Special thing in designing a overhead reservoir ? which is different from an ordinary design
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same
In a concrete grade C35A, C & A stands for what and equalent cube strength?
Which Types Of Bricks ?
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
if we know load bearing capacity of the soil and building load falling in each footing, then how to choose the type of foundation??? and if it is shallow foundation then which type of shallow foundation should be choosen i.e either strip or isolated or raft or combined or cantilever footing???????
What is the software used in civil engineering?
how to calculate the chair reinforcement length in slabs, footing or anywhere??
which steel is better for residential building tmt steel or hysd steel
how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab
can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com
what are the ffactors you considered choosing the course?
How much cement,sand,bricks and water needed for 1square metre brick work?