in our transmisison sub station why we step down firstly
132kv\33kv then 33kv to 11kv. can we direct step down 132kv
to 11kv.
Answer Posted / manish
Yes you can directly stapdown 132 kv to 11 kv but in
general cases our transimision outgoing feeder may be
66kv,33kv or 11kv thats why we stap down 132/33/11kv ,if 33
kv not required then we can direct stapdown 132kv to 11kv
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
Could Please Explain briefly. Why used stabilizing resistance series with High impedance bus differential protection relay.
I completed iti in2004 I was worked in A grade contractor can I get c licence
What will be result if we connect LT votage to the terminal of HT motor?
how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING) I O (current operating)?
What is “pu” in electrical engineering?
why EMF IS INDUCED IN A CONDUCTOR WHEN FLUX LINKING WITH IT CHANGES ACCORDING TO FARADAYS LAW.
how to read idmt curva
iam working in power plant. In hot places tube lights are glowing at the end portion only. what is the reason for that?
Give me the calculation steps to design an electromagnet to be work in 230V 50 Hz AC Supply. Also give force that is created by that electromagnet when it gets energized.
dg started in plc mode and load taken later one battery terminal connection will be disconnected by loose connection what will happen for dg and shall we connect battery terminals while dg in load time?
regarding safety what would u consider the most important rules to observe when inspecting electrical equipment?
what is meaning of bus riser
Differentiate between ideal and non-ideal voltage sources?
how to select electrical equipment such as fuse,dg,transformer,motor,msb,wire,cable as per the connecting load..please mention any books to design,take licence
what is the most permissible winding temp when we conducting a generator load test?(condition no load)