what is period of de-shuttering for different area of slab
of M25 grade?
Answer Posted / n.c.pathan.
It depends upon the span of the slab. For spans less than
6m we can remeve the props after 14 days and in case of
spans exceeding 6m we can remove the props after a period
of 21 days.
Is This Answer Correct ? | 30 Yes | 5 No |
Post New Answer View All Answers
what are the code used for residental building?
What are the advantages of cad?
Explain what is Hybrid Foundation?
What sizes of stones chips are used for foundation, column and floor casting. Please answer in detail.
i want texture painting pwd data
What is absolute coordinates?
psc girder detail
why is the column design?
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
What glue is least sticky?
sir how can we find the cement and sand required for making 4" drop
For what purpose bedding is used under storm water drains, explain?
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
Which is the direction of negative angle?
What is meant by scaffolding coefficient?