what is period of de-shuttering for different area of slab
of M25 grade?
Answer Posted / n.c.pathan.
It depends upon the span of the slab. For spans less than
6m we can remeve the props after 14 days and in case of
spans exceeding 6m we can remove the props after a period
of 21 days.
| Is This Answer Correct ? | 30 Yes | 5 No |
Post New Answer View All Answers
how to balance aggregate during mix design of concrete???? how to calculate moisture content like C/A,F/A and how many percentage using ice instead of water for example of we are preparing ice concrete??????
Define What is diversion tunnel in a dam?
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
Which prize is the alternative to the NOVEL Prize?
how to calculate the size of triangular ring in rcc column?
water leak detection system question & answer
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
Formula of mid span bar
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
all technical question
how to find ssm in foundation?
how to calculate total cost for slab 35'×8'
how to caluclate sienerge qty in construction in ap