what is period of de-shuttering for different area of slab
of M25 grade?

Answer Posted / n.c.pathan.

It depends upon the span of the slab. For spans less than
6m we can remeve the props after 14 days and in case of
spans exceeding 6m we can remove the props after a period
of 21 days.

Is This Answer Correct ?    30 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what are the code used for residental building?

2041


What are the advantages of cad?

629


Explain what is Hybrid Foundation?

734


What sizes of stones chips are used for foundation, column and floor casting. Please answer in detail.

1668


i want texture painting pwd data

1632






What is absolute coordinates?

687


psc girder detail

2696


why is the column design?

1820


I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com

1829


What glue is least sticky?

678


sir how can we find the cement and sand required for making 4" drop

1628


For what purpose bedding is used under storm water drains, explain?

729


We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?

1588


Which is the direction of negative angle?

619


What is meant by scaffolding coefficient?

2175