what is period of de-shuttering for different area of slab
of M25 grade?
Answer Posted / n.c.pathan.
It depends upon the span of the slab. For spans less than
6m we can remeve the props after 14 days and in case of
spans exceeding 6m we can remove the props after a period
of 21 days.
| Is This Answer Correct ? | 30 Yes | 5 No |
Post New Answer View All Answers
what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????
what is the effect of duration of earth quake on framed structures ?
What Reinforcements Are Used In The Process Of Prestressing?
what is the difference between np2 and np3 concrete mix
Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?
How to determine spacing of bars in slabs or beams
why does the most of civil engg is not intersted to going for teaching field?
How to calculate material and labor required for 100 m2 plaster?
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?
what is thumb rule for calculating the size of ISMB required for a particular length of span
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
What is the use of offset command?
What happens to Load at yielding ?
how much cement and sand required for 100sqm of wall plastering in different proportions
How do you calculate the power of a centrifugal pump?