Answer Posted / ch amir islam
We use CASECAD loop to inhance the capability of the
process.normally we use this loop at BFW(boiler feed water)
tanks and at the BMS(burner managment system)to inhance the
burning ratio of fuel that become more relaiable for our
firing.because we are using here two controller(two
setpoints)these both controller makes process much more
flexible and accurate.
| Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
what is the procedure of O2 sensor(ABB) calibration?
Draw a great bridge circuit.
what is compensation? temprature & pressure
TECHNICAL/ARTITUDE
i hav applied for the post of engg. in iocl so please require the past test papers fro instrumentation engg please please help me and send me the papers or tell me the pattern and type of ques asked in examination......
How to calibrate smoke Dectector
Explain about the leakage class of the control valves
For crude application in floating roof tank, how to calibrate a DP Transmitter? How is the floating roof weight considered?
What is instrumentation technologists and mechanics?
what are the values of fuel flow rate in various places in boiler.
we are having yokogawa centum cs3000 dcs in our power plant. i need some of the operator guides NOT to appear in HIS0163 AND HIS 0162 but it shoul appear in HIS0164 HOW TO DO IT?
How r the calculation of process line mpm.
How we can check the 2 wire proxy switch? & how it is connected to DI MODULE OF PLC?
IS there any effect of vortex in low pressure side of the transmiter after the orific in feed water line? if yes then what is the calculation?
Which tank weighing system is better to install (Accuracy point of view) 1) Tank weighing system with 3 load cell or 2) Tank weighing system with 4 Load cell