Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what do we mean by hook up drawing. what r the information we
get from it?

Answer Posted / denizen360

hook up drawing is a which represent the connection between
the instrument and process line..
which is used to prepare bill of material..
2 types of hook up are there..
1.pneumatic hook up
2.process hook up

source: http://instrumentpedia.blogspot.com/2010/12/what-is-
hookups-drawing-and-how-to-read.html

Is This Answer Correct ?    7 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

I am teja. I am studying Msc(tech) Electronics and Instrumentation (3years course) in Andhra university. But my course is not recognised by UGC and AICTE. Please tell me the job opportunities after this course. And i fineshed PLC course in IGIAT ,Vizag.Also complted my short term coure in SCADA, Seimans WinCC in ATI,Hyd.After Msc can i join Mtech for good job? or phd. How i can get good job in INdustrial Automation Side. Please give replay.Because this is my life matter.

2020


how do u calibrate the vacuum transmitter if it shows more reading

1988


Specify eight technical requirements that you would consider important, when deciding upon a particular control valve?

1822


Where are oxygen analysers installed in cfbc boilers? What are their usual readings?

1480


What are different types of orifice plates?

1106


How to work temperature gauge?

1811


Isometric drawings are generated during _________________ phase of a project

2016


There are two chlorination tonners both are connected to two pressure swithes and the pressure switch is connected to SOV which operates the valve to changeover the tonner selection i.e if pressure one tonner goes low the other tonner should come in line if it is inautomatic selection design a circuit using relays ?

1904


Sir , i have completed my M.Sc In Instrumentation and presently working in Maintenance department 3 yrs Exp , is there is any possible for work in offshore ..

1792


How to convert milliampares into flow??

1663


what is interlock system and why we use of this?

1959


Hi,can anyone help me out with PhD programs related to Instrumentation field?I have a degree in electronic Instrumentation?

1867


how u choose thermowell lenght n pnumatic C/v size?

2048


god evening sir i am studying m.sc(tech)electronics &instrumention.am i elegible to all industies

1762


how to check earthing,what is minum ohms for proper earthing

1879