I decided to provide a 11KV / 440V Xformer in my Substaion.
What are the protection required for that?
Answer Posted / doli tomar
11000/440v means it is step-down transformer.so, for MV
side use 9kv LA,11 kvDO-FUSE and switch gear panel which
includes VCB which is used for isolating the transformer
during maintenance period.For LV side use 4P ACB /MCCB for
3-
phase bus bar(R,Y,B) and use overcurrent, overvoltage,
undervoltage,IDMT,Single phase preventer,restricted earth
fault relay because Relays are used where it is necessary
to control a circuit by a low-power signal (with complete
electrical isolation between control and controlled
circuits), or where several circuits must be controlled by
one signal.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
if an insulated power and control cables of a running gas diesel gensets laid direct in an open trench i.e, trench bed is not rcc of a power house in which rain water, spillage water alwas exists and all power control cables remains submerged even when gas gensets of 480 kw each runningin on load. These power &control cables runs from power house to switchgear room through these trenches in which water remains most of the time. pl explain its merit & de-merit
WHTA IS LIMT OF LEAKGE CURRENT OF 11 KV 1 CORE 1000SQ.MM. XLPE CABLE.LOAD ON CABLE IS AROUND 600AMP .LENGTH 500 MTRS.
what is meant by poly phase induction motor ? how its operating by single phase or three phase?
what will be happen if earth point is being used for as a neutral point for raw power , and same will be used for ups earthing
Please clarify, 1. Is it required to lay two runs of GI wire along with Armoured LT cable if it is laid between one big mains (63Amps TPN SDF) to small main (32A TPN SDF) with proper glanding termination? 2. If the armoured cable with proper glanding is laid from DB to CNC machine, is it required to run two runs of body earthing to the Machine from DB? 3.If the armoured cable with proper glanding is laid from Substation to Hangar, distance is approx. 100 mtrs, is it required to do earthing at shop area though the primary termination at substation is earthed through gland.
Whats the difference btwn a latch, port,data bus buffer? Do they all not hold data in d flip flops??
HOE WE CAN IMPROOVE BY USE OF CAPACITOR
What happened when voltage will half value of current ...
When a square wave is applied to primary of a transformer then what will be output wave form of secondary ?
how we can calculate the efficiency of a diesel generator ?
what irequirment need to be followed when working on live equipment
Define resonant frequency?
I am using submission of two ct in one and half scheme for 67/67N protection. Both CTs star point is grounded separately near ct box.Will two point ground give wrong tripping to 67/67N during fault or no matter.
WHICH SIZE A.B.CABLE IS USED FOR 11KV.
hi this is hema can anyone mail me previous years questions for the APPSC-A.E.E (in electrical stream.) ......thank u.