cover. Thanks.
Answer Posted / pvsnrao
Let us take, b = bredth of the beam
D = Overall depth of the beam.
Effective depth = overall depth-effective cover
effective cover = the distance from botttom of fibre of the
beam to the centre of reinforcement.
Clear cover = the distance from the bottom of fibre to
bottom level of the reinforcement
| Is This Answer Correct ? | 209 Yes | 23 No |
Post New Answer View All Answers
What is the unit standard weight,thicknessof C.I>Pipe of various Dia upto200 MM(as per IS1538)
Specific gravity of cement?
what is tension column?
how many litres of enamel paint required for 5000 sft of site??
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
what is cross hair cursor?
What materials were used to build the golden gate bridge?
Define angular dimension?
what is the use of beam end forces while using a staad ? wha they are show
How many pyramid in egypt?
How to find CN by using arcgis 9.3?
Does degree of bend of rebars has any effect on strength of the member? For example- if a beam is designed with 45 degree bent up bar with respect to architechtural needs and is not 45 in practical so will there be any reduction in the strength of member?
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
what is the types of surveying?which type of survey carrying for type of work?