Please tell me the difference between nominal and clear
cover. Thanks.
Answer Posted / pvsnrao
Let us take, b = bredth of the beam
D = Overall depth of the beam.
Effective depth = overall depth-effective cover
effective cover = the distance from botttom of fibre of the
beam to the centre of reinforcement.
Clear cover = the distance from the bottom of fibre to
bottom level of the reinforcement
Is This Answer Correct ? | 209 Yes | 23 No |
Post New Answer View All Answers
WHAT DLC DESIGN IN CONSTRUCTION
how many re use can use shutting material. timber ? ply? steel? plastic? fibre? aluminium? Doka?
Formula of mid span bar
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....
What is difference between combin footing & rapt footing
what is cement wastage percentage in NHAI ROAD WORKS
in the construction of residential building what type of tank are used?where?why & what is its purpose?
Trapezoidal section footing calculation of Volume & its Area
Why do we not deduct steel volume to find actual volume of concrete in practical as we have studied that,,, actual volume of concrete = volume of column- volume of steel pls explain with reference of IS code?????
The largest size of paper used in plotter to print the drawing made by Autocad .
Design a cantilever type retaining wall to retain sand for 4m above the ground. The sand fall slopes at the rate of 1 vertical to 2 horizontal. The weight of sand is 18000 N/m3, the angle of repose being 30. The safe bearing capacity of the soil is 200 kn/m2 at 1/25m below the ground level. Use m 15 concrete mix.
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal