Answer Posted / alan
"Factory calendar contain company specific dates such as
alternate working Saturdays, Plant shutdown etc.
"You can create your company factory calendar via
transaction code 'SCAL'.
"Assignment of the factory calendar by plant is done in
transaction code 'SM30 - V_T001W'.
"An example of a SAP application that uses the factory
calendar is the SAP MRP modules.
"Assuming that you have a specified an alternate working
Saturday, MRP will postponed the planned orders to the next
working day if it happened to falls on a non-working
Saturday."
| Is This Answer Correct ? | 21 Yes | 2 No |
Post New Answer View All Answers
What is a partner type? Give some example?
In interviews interviewers asked me "what is your responsibility in your project?". what is the answer for this question. Pls tell me the answer anybody. Thanks in advance.
Diff between business sale cycle nd customer sale cycles?
Do you know what is made to order scenario or make-to-stock scenario? SO, in the make-to-order scenario, what’s the integration touchpoint that you figure MRP? My question is when you have a make-to-order scenario, how does MRP will be figured? How system know that when you create a sale order whether the sale order is calling for make to order or make to the stock type of order, which data determined this is made to order make to stock…. The system should understand when I create an order, whether it’s made to order or make to stock, so which parameter which value that system will be determined based on that system will say okay this make to order so I need to I mean the system has to go to the next level then it’s going to the MRP all the subsequent planning will be taken taking place, what’s the parameter that we have to check?
What and where types of copy controls we change
What’s forward scheduling and backward scheduling activator? There’s a concept called forward scheduling and backward scheduling logic when you do an availability check whenever your order is created system will check whether it’s forward scheduling or backward scheduling, if it’s fatal we have a concept of how is it working, how is that you created as part of your available promise concept? Whatever that date is being considered as part of the logic, whatever the date that is configured or we maintain the data to say know that system tell to create this output back scheduling
What is the procedure to know whether the customer is one-time or regular?
when we create customer it is showing one message GENERAL DATA ALREADY EXISTS ACCOUNT AS ACCOUNT (GROUP HIRARCHYNODE)WHAT IS THIS ?CUSTOMER IS CREATED BUT GENERAL DATA VIEW CONTAILS ONLY 2 VIEWS (MARKETING,CONTACT PERSON)REMAINING IS NOT SHOWN WHY IT IS?
How to create the source and target database connections in the server manager?
Give a definition of plant (in sap).
How is the shipping point determined?
Are you familiar with the partner profile setup? I am sure when these EDI transactions must have been posted through SAP as idoc?
What are the different complaint process documents in sap sd.
What is a standard transport layer in sap ? : transportation management
What is the business process of excise tax and how do you relate that in sap?