Answer Posted / sivasankar
The base range of the electronic transmitter out put is 0
to 16 mA. but during measuring through a series DC volt
connection (24VDC)the negative reading could not be
justified either the result is wrong polarity or the actual
negative reading below Zero value. So international
accridation has decided to elevate the zero value from 0 mA
to 4mA and straight way increased span value also from 16mA
to 20mA.(as an equal increment in 5 step 0%,25%,50%,75% and
100% of out put). Generally the electronic sensor base
output reading trimmed with 2.99 to 3.22 mA from
manufacturer. if the sensor is in good condition it will
show the base reading. 5 to 20 mA reading is not accepted
in industry so far.
Is This Answer Correct ? | 20 Yes | 14 No |
Post New Answer View All Answers
why we should maintain neutral earth voltage below 1V while calibration? why cant it be 1.2V or 2V
Senior engineer's please help me, what is Loop Checking and Loop test? and write difference also? soon urgent
Manipulation of dead wt. tester double piston type.
Can anyone send most commonley asked Instrumentation questions and answers in cement industry please?
Why do we have earthing cable in branch cable and shield in the same cable?
1)How many tpes of vibration probe and how many tpyes of vibration. 2)how we can calibrate a vibration probe with tk3 3)what is RMS value in vibration measuring application and how we calculate it.
What is stripper & spilitter ? Diffrence in this.?
Describe the typical instrumentation used in monitoring the performance of a shell and tube heat exchanger.
What are the maximum packet size of: a) HART b) Profibus DP c)Profibus PA d) DeviceNet e) Foundation Fieldbus
Which products are available in the Mass Systemswitch and System Manager AC range?
what is the procedure to callibrate temp controller ,pressure controller,etc. suppose a temp controller showing error 1.5 degree centigrate how can i minimize it.
describe flow nozzel principle?
Im having problems with interfase betwen SPI v7.0 and SPPID v5.05. Previous versions of Intools shoul be fixed with SPPIDproj.ocx file. It was necessary to replace this file with one that allows the connection between different versions of SPPID. It is necessary in the current version to do the same?Thanks
What is 1:1 redundancy ?
hi friends,im an instrumentation and contol engg student,can u hlp me of suggsting barc written question paper,my id is roysuvaranjan@gmail.com, cel no.9563591747