how to prepare analysis of hire charges for 62.5 KVA
generator
Answer Posted / shyam.bh
It is a lengthy & detailed process for rate analysis of
equipment.
It is done by the CWC (Capital cost & Wages of Crew) guidelines.
Hourly charges of 62.50 KVA DG
basic cost = 4,00,000.00
add transportation & insurance charge = 32,000.00
Other taxes = 12000.00
Book value of machinary = 4,44,000.00
Rated life = 08 yrs
Rated life in hours = 20,000hrs
Yearly depreciation of the equipment = 49950.00 (cwc
guideline)
hourly depreciation = 20.00 -----A
Interest on capital investment/hr = 16.00 -----B
Repair & maintanance@120% = 24.00 -----C
Fuel charges for operation = 0.026*62.50/0.746*3.04*35
= 232.00
Oil & lubricants @ 25% of above = 58.00
sundries @ 10% of repair charge = 2.00
Total fuel charges = 292.00 ----D
Labour charges
rated life / month = 12000/144 = 166.67 hr/month
regular worker
operator = 8,000.00x0.80 = 6,400.00
mechanic = 10,000.00x0.125 = 1250.00
Total L/C = 7650.00----a
Casual worker watchman = 3000x0.125 = 375.00 ----b
Total L/C = 8025.00
Add hidden charges @ 80% on 'a'& 55% on 'b' =6326.25
Total L/C = 14351.25
Hourly L/c = 86.10 ----E
therefore the hourly charges of a set 62.50KVA
= A+B+C+D+E = 438.20 Rs
| Is This Answer Correct ? | 10 Yes | 0 No |
Post New Answer View All Answers
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
What is specific gravity???
1m square 20mm plastering how much of water need curing work
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
Mention what are the composition of a landfill?
Why are pull-out tests performed for soil nails?
what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15
how can calculate cutting length of diamond ring
Define Who designed the city of Washington DC?
what are RIB slabs explain about it
how to conversation of all construction material in to brass
Explain the various stages of the project planning process in construction?
in one hour , one 200 excavator , how much quantity (mcube)can load ? soil is not hard not soft
sir, whitch is the best book (writer name) for prepration of gate....
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?