how to prepare analysis of hire charges for 62.5 KVA
generator
Answer Posted / shyam.bh
It is a lengthy & detailed process for rate analysis of
equipment.
It is done by the CWC (Capital cost & Wages of Crew) guidelines.
Hourly charges of 62.50 KVA DG
basic cost = 4,00,000.00
add transportation & insurance charge = 32,000.00
Other taxes = 12000.00
Book value of machinary = 4,44,000.00
Rated life = 08 yrs
Rated life in hours = 20,000hrs
Yearly depreciation of the equipment = 49950.00 (cwc
guideline)
hourly depreciation = 20.00 -----A
Interest on capital investment/hr = 16.00 -----B
Repair & maintanance@120% = 24.00 -----C
Fuel charges for operation = 0.026*62.50/0.746*3.04*35
= 232.00
Oil & lubricants @ 25% of above = 58.00
sundries @ 10% of repair charge = 2.00
Total fuel charges = 292.00 ----D
Labour charges
rated life / month = 12000/144 = 166.67 hr/month
regular worker
operator = 8,000.00x0.80 = 6,400.00
mechanic = 10,000.00x0.125 = 1250.00
Total L/C = 7650.00----a
Casual worker watchman = 3000x0.125 = 375.00 ----b
Total L/C = 8025.00
Add hidden charges @ 80% on 'a'& 55% on 'b' =6326.25
Total L/C = 14351.25
Hourly L/c = 86.10 ----E
therefore the hourly charges of a set 62.50KVA
= A+B+C+D+E = 438.20 Rs
| Is This Answer Correct ? | 10 Yes | 0 No |
Post New Answer View All Answers
Why should you show Client/Engineer activities clearly on the project plan?
what is concrete canvas?
What is the name of this multiplication factors ?
how many digree of freedom in four bar chain
how many minimum admixtures are used in water froofing structures
I need to constructive work in amaraj batteries
where can i get the previous question papers for rrb section enginerr (civil)
what is the metal ratio in granular subbase coarse for one cum ? And please explain the morth table ...what is the difference between grading 1 , 2, 3 what it means..plz explain
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
what are the ffactors you considered choosing the course?
In block work seawalls what is the purpose of slip joints?
What are the advantages of cad software’s?
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
why do we provide haunches in rcc box or underpasses?
What is progress payment?