present we are having 0.8pf but I want increase it up to
0.99 so what is the formula for it and how can i calculate?
Answer Posted / at
if you want to increase the power factor from 0.8 to 0.99
then in that case for
1. Generators:- you will have to increase the excitation
when generator is connected in an interconnected system
i.e. Many generators operating in parallel / or connected
to grid. increasing the excitation gives a leading power
factor and under excited generated draws lagging power
factor power.
2. When it is the case of Industries or other utilities
consuming electrical energy. one should know that all loads
consuming power are 99.99% inductive loads.Thus by adding a
capacitor bank of suitable rating shall be required to
compensate the lagging power factor.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
WHat is the requirement of installing FAST ACTING EARTH SWITCH in GIS and how is that integrated with protection system. How and when does it operate?
how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING)IO (current operating)?
How to calculate approximate load loss of a distribution transformer by knowing %ge imp of transformer?
If increased the frequency up to 1000 then what changes shows in voltage?
Use of switch mode power converter in real-time basis?
1 “earthing” for bonding of equipment and circuits to common plant earth electrode potential, 2 “protective earthing (PE)” when this bonding is required for personal safety provisions 3 “grounding” for interference suppressing bonding of screens, sys-tems with ground level 4. low-impedance earthing ? 5.primary earthing system and secondary earthing system what is that? 6.earthing electrode or mesh net earthing electrode ? very confusing , simple but very informative help required ? i will be very very thankful to you guys.
How can we calculate cable size in Low voltage & high voltage
WHat is the general checks required for Dry type transformers
what is the difference between b c d curves on mcb
all interview questions with answers of ntpc (2000-2009
Lt motor sfu flashing reasons?
While testing a ZCT what parameters have to check or measure?
why we have and use 3 phase not 2 or 4 or other in power system?
can you please send me the technical questions and aptitude questions of honeywell and jindal steel electrical engg. question paper my e-mail ID is(kkesavanraj@gmail.com)
How you give clearance to a spare feeder.