Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

The neutral to earth connection in my industry is showing a zero reading
(shorted). I have a machine which has to be installed where neutral to earth is
not shorted and shows a leak voltage <3 Volts. Please suggest me how it is
possible.

Answer Posted / nadir

Possibly your machine required an IT wiring which is unearth neutral. Your machine may required only a PE and the PE electrode shall be installed at a distance of 1.5 longer than your transformer/ neutral earth electrode length.

The isolation transformer will also create harmonics and required to dissipate.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

draw vector diagram and +ve,zero sequence diagram of symmetrical three phase fault.

2018


Dear all, how we select the cable size according  to current with or without including different correction factor , is there any direct method for sizing of cable... 

2148


what is the necessary of using inductance property in transmission lines even through resistance is used to opposes the high current flows in that?????

1868


WHAT IS THE WINDING PROCEDURE OF ELECTRICAL MOTOR

3966


What type of fittings and electrical accessories can be install in radiation area ?

1738


what do you mean by class PS CT and what are technical details needed for calculating it?

1973


for what purpose the star point is done in ct

1393


why the carbon brushes are broken in srim while the motor runningtime

1686


How to calculate the electrical load for a standard telecom BTS shelter and choose the DG set capacity for the same load?

3171


What are n circles?

1073


What happen to the transformer if the OLTC frequently used for lower and raise occured 50times daily?

2027


Define peak overshoot.

1251


what the function breaker failure scheme, how is it operated

1893


What are the main parts of central chiller plant? Explain the function of each stage.

4785


Load transfer in 11kv double busbar switchgear - operation.

1935