curing of concrete why 7day's,14day's 21day's 28days
Answer Posted / guest
After concrete is placed, a satisfactory moisture content
and temperature (between 50°F and 75°F) must be maintained,
a process called curing. Adequate curing is vital to
quality concrete.
Curing has a strong influence on the properties of hardened
concrete such as durability, strength, watertightness,
abrasion resistance, volume stability, and resistance to
freezing and thawing and deicer salts. Exposed slab
surfaces are especially sensitive to curing. Surface
strength development can be reduced significantly when
curing is defective.
Curing the concrete aids the chemical reaction called
hydration. Most freshly mixed concrete contains
considerably more water than is required for complete
hydration of the cement; however, any appreciable loss of
water by evaporation or otherwise will delay or prevent
hydration. If temperatures are favorable, hydration is
relatively rapid the first few days after concrete is
placed; retaining water during this period is important.
Good curing means evaporation should be prevented or
reduced.
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
What is a hatch patterns?
pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width
What is reinforced concrete?
How much form and scaffolding per cubic meter volume of concrete class ''A'', ''B'', and ''C''
need to join coaching institute in coimbatore tamilnadu ......say me the best coaching for IAS
States some of the commonly used commands in cad software’s?
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
how to calculate freeboard in under ground water tank and technical details
how many kg of 20mm, 10mm, dust available in one ton stone boulder
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
For fine aggregate which is most suitable River sand or crusher sand & why ?
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
how i get all type of short type question answer about civil engg
In earth work 1300 cum soil how to calculate how many liters require in water