how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / adishankar (quantity surve
DETAILS:
cement = 1,
sand = 2
metal = 4
so wat is the ratio we want mixing (1:2:4)=1+2+4=7
7 is mixing propotion
volume of wet cement conceret is 1.54 to 1.57
unit weigth of cement is 1440kg/cum
one bag of cement =50/1440=0.034722 cum
solution : cement = 1.54/7=0.22
0.22/0.03472=6.33 bags
one bag of cement = 50kgs
=6.33*50kgs=316.82 kgs
solution of sand = 0.22*2=0.44cum
2 is the mixing of propotion
soolution of metal = 0.22*4=0.88cum
4 is the mixing of propotion
say i cum of cement conceret 1:2:4 ratio
cement = 6.33 bags
sand = 0.46 cums
metal = 0.88 cums
this is one type of solution
unit weight of cement is 1440kg/cum
sand 1660 to 1800kg/cum
Unit weight of metal is 1630kg to 2000kg/cum
so cenment = 1.54/7=0.22
0.22*1440=316.8 kgs/cum
sand = 0.22*1750=385kgs/cum
metal = 0.22*2000=440kgs/cum
Is This Answer Correct ? | 554 Yes | 92 No |
Post New Answer View All Answers
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
How to design staircase.plz tell me formula for the design the staircase.
what is m30 in concrete tiles
what"s the sort of beams?
How do you prepare Material Recovery Statement for deduction from contractors bills?
how many re use can use shutting material. timber ? ply? steel? plastic? fibre? aluminium? Doka?
i want texture painting pwd data
how do you calaculate the total steel quantity of an rcc building using thumb rule?
how we check the thickness and line of ceiling plaster.
What is the basic difference between OPC
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.
How will you Engage Labours on Site?
it is a corrected question." make a list of engineering property(properties) of soil.
how to clculate the %of concrete strenght achive after curing?load
How to build the floor to ceiling bookcase?