How to take Vector group test of Transformer?
Answer Posted / vinod
Vector group is punched on the name plate based on the user
requirement by the manufacture. Aim of vector group test is
at site is to check if their is any damage in the windings
during transportation and erection.
3 -phase AC supply is given on HV side. R-Phase HV and r-
phase LV shorted for all vector group of transformer
Then to qualify the test following conditions are to be
satisfied after measurement of voltages.
nR+nY=RY, By>> Bb and Yb=Yy.
| Is This Answer Correct ? | 19 Yes | 5 No |
Post New Answer View All Answers
Name the test signals used in control system
what is a bus post insulator? explain its application in a substation.
Tell me about ur past electrical maintanence job
explain Density
why swinburnes test cannot be performed on series machines?explain
in 1-phase 230v,how in 3-phase 440v. in each phase in between 230v.
what are types of encoder
how is the cable tray designed & how its total length is calculated for an Industrial plant Say for Ex. (500KW Motor Load)
how does a shunt reactor maintains the bus voltage???
Rules and standards of electrical control wiring ?
How relay coordination has to be done? what are the inputs are required for this? Please explain this with calculation method?
What happened when capacitor connect series in ac circuit?
how generator load test is conducted?what are the steps?
what & how to check the lightning arrester
What is current & voltage ? Voltage perform at any load without current or not?