The Project which is handled by you is in RED, customer has
given you 4 weeks to show improvement, still nothing has
worked out. The Customer again gives 3 weeks to improve and
you do your best to improve, but nothing works out. Now the
customer is not at all happy, HOW TO CONVINCE THIS
CUSTOMER ???
Answer Posted / madhavi bhave
The situation indicates failed requirement, time and
communication management. First and foremost will be to do
the analysis, confirm the deliverables, check the work break
down structure and check the status of schedule against the
deliverables. Then to identify the improvements which
customer may not have realised, estimated time for
individual deliverables. with this statistics in hand, fix
up a meeting with the customer. Take him into confidence,
thank him for giving you time, appraise him of the real
situation and probably what went wrong according to you.
Tell him about the quality improvements (if any) and discuss
with him the estimated schedule with deliverables.
| Is This Answer Correct ? | 49 Yes | 2 No |
Post New Answer View All Answers
What is tracing process? How this can be enabled?
You are a project manager for a documentary film company. In light of a recent national tragedy, the company president wants to get a new documentary on the rescue efforts of the heroic firefighters to air as soon as possible. She's looking to you to make this documentary the best that's ever been produced in the history of this company. She guarantees you free rein to use whatever resources you need to get this project done quickly. However, the best photographer in the company is currently working on another assignment. Which of the following is true? A. The primary constraint is time because the president wants the film done quickly. She told you to get it to air as soon as possible. B. Resources are the primary constraint. Even though the president has given you free rein on resource use, you assume she didn't mean those actively assigned to projects. C. The schedule is the primary constraint. Even though the president has given you free rein on resource use, you assume she didn’t mean those actively assigned to projects. The photographer won’t be finished for another three weeks on his current assignment, so schedule adjustments will have to be made. D. The primary constraint is quality because the president wants this to be the best film ever produced by this company. She's given you free rein to use whatever resources needed to get the job done.
The purpose of the Initiation process is to: A. Formally recognize the existence of a project or project phase B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technological advances, or legal requirements C. Formally recognize the stakeholders of the project and identify them in the project charter D. Formally recognize the project sponsor and document his or her project goals
All of the following are true regarding parametric modeling except: A. It's a form of top-down estimating. B. It's a mathematical model. C. It's a tool used to estimate project costs. D. It's a tool used to estimate project time.
Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero. ?
Which organization has set the de facto standards for project management techniques? A. PMBOK B. PMO C. PMI D. PMA
What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action
As a PMP, one of your responsibilities is to ensure integrity on the project. When your personal interests are put above the interests of the project or when you use your influence to cause others to make decisions in your favor without regard for the project outcome, this is considered: A. Conflict of interest B. Using professional knowledge inappropriately C. Culturally unacceptable D. Personal conflict issue
Explain on the project management life cycle process?
You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower's site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What do you know about this project? A. The EAC is a positive number, which means the project will finish under budget. B. You do not have enough information to calculate CPI. C. The CV is a negative number in this case, which means you've spent less than what you planned as of the measurement date. D. The CV is a positive number in this case, which means you're under budget as of the measurement date.
You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and have reviewed the contracting process to identify lessons learned. What is the name of the tool and technique of Contract Closeout you used to perform this function? A. Procurement audits B. Performance reviews C. Performance audits D. Procurement reviews
You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.
You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. The stakeholders have accepted the project scope. Work has begun on the project, and you're confirming some of the initial work results with the stakeholders. You've asked for acceptance of the work results. Which process are you in? A. Quality Assurance B. Quality Control C. Scope Verification D. Performance Reporting
Which of the following are the outputs of the Contract Closeout process? A. Project archives, formal acceptance and closure, contract file B. Contract file, formal acceptance and closure C. Project archives, contract file D. Contract file, formal acceptance and closure, lessons learned