How can we cross check the excavation and backfilling
quantities.
Answer Posted / praman srivastava
In case of foundation like Load Bearing , Isolated footing
or raft , Total excavation calculated as per plan & require
depth form NGL & deduct the total qty of pcc cc or B/w up
to NGL,then total balance qty is known as backfill.Approx
60% qty.of excavation is required for back fill.
| Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
How much percentage of brick bats allowed in CD-75 bricks
how do we calculate quantity of cement sand and aggregates in 1m3 of m20 m25 grade concrete?
how to stop beam concrete between column
what is tension footing?
How to determine dia of steel for use in column,slab etc. i mean how to calculate the diameter of steel which is to be used in structures.
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
residential projects,structural.
What is alternate bid?
WHAT DLC DESIGN IN CONSTRUCTION
For what purpose bedding is used under storm water drains, explain?
in 2 way slab can additional compressive reinforcement can be provided if yes than in which conditions it is required ?
What are the benefits of rcc pipes over steel designed pipes?
I am called for interview from north east power plant .so, I need some interview question which may help me.