A single line diagram(SLD) and a purchase order of a
11/66kV switchyard of a power plant was given. In the SLD,
only one lightning arrestor(LA) was shown, but the purchase
order had need of 3 LAs. Is this correct, if yes, why?

Answer Posted / k.prakashchandra

We have 3 phase Tr ,breaker,G.O.S. but no 3 phase L.A.

Is This Answer Correct ?    2 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Dears we deal in Chemical are Plate earthing. Kindly call if any requirement and questions. Tech Earth Solutions Mohit Verma 8791071007

1397


what is the use of Auto re-closer?

1644


What is the function of the circuit breaker failure relay?

1900


How to find out damper winding failure for synchronous machine?

999


salam&hi, i need to know about how can i calculate an enough current for the new building before i submit it to the suppliers

1612






Explain the process of commutation in a dc machine.

604


how we can find of current direction(supply comming/out going direction) when a transmission line passing through sides.

1909


working principle of oil startar

1451


What happens if the series current double?

994


what is the difference between the characteristics of two different phase bushing of any transformer

1340


how could we know the size of cable by physical view?

1215


HOW WE CHOOSE EARTH'S POTENTIAL AS ZERO V?

1601


A 1F capacitor is charged to 100V initially. A 1H inductor is connected accros the capacitor througha a switch. The current in the circiut when the switch is closed is____

1868


I am going to appear for the RRB Chennai junior Engineer online exam. Please send me the previous exams question papers (also solved) to my mail id: rrkhandhar@yahoo.com

1522


What will happened if the neutral of secondary of Xformer ( Star point) Note it's above KVA rated Xformer

1417