A single line diagram(SLD) and a purchase order of a
11/66kV switchyard of a power plant was given. In the SLD,
only one lightning arrestor(LA) was shown, but the purchase
order had need of 3 LAs. Is this correct, if yes, why?
Answer Posted / sakthivel
IT IS CORRECT WE REQUIRED 3 LA IN 3 PHASE
| Is This Answer Correct ? | 16 Yes | 2 No |
Post New Answer View All Answers
What is MS-EXCELL?
why do we carry out winding resistance test?
What is the function of probe in cro?
What is servo motor and what are different types of servo motor
what is rating boiler
i want to know how to determine that a surge arrester work properly in 11kv system. and how to test a 12kv surge arrester
Why hydropower is called renewable source of energy?
How will A Medium voltage circuit breaker(11 kV voltage level) operate under short circuit fault condition whether It is having short circuit release like Low voltage circuit breaker or relay should be given?
What are the difference between normal application Transformer and Solar application Transformer?
What is fault clearing time for Current Limiting Moulded Case Circuit Breaker?.
Why cables and busbar both needed in LT Panels?
Usage of flywheel diode in relays
UG cable sizes were specified in sqmm. But practically its not coming to mesure. What's the reason for that? And how they specify the size of the cable?
Sir, I have applied for the of Jr.engineer(Electrical & Electronics) & ASST. LOCO PILOT at ALL RRB BOARDS. please send me all RRB Boards solved papers in the year of 2001 tO till date. i requested send me the papers to my id as soon as possible (jet_0991@yahoo.com). (This is very urgent) Thank You,
What is a difference between indoor transformer and outdoor transformer of same rating