Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

125Kva Dg can take up how much amphere load.

Answer Posted / guest

V= 415
KVA = 125


A = KAV/V*Root3

= 125/415*1.732
= 173.905 Per Phase

Is This Answer Correct ?    54 Yes 12 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

it is possible to measurement of tension of slipring induction motor(SRIM)carbon brushes, any maesuring instruments are available in the markets.

2000


if voltage bt phase & nutral is 38v in a panel board . whats the root cause.

2309


I want formula to calculate cable size as per load given in length & amp. I searched many sites but didn't right answer. Please reply me asap.

1468


why is the conservator tank painted white on the transformer

3182


If we need 4c× 50mm sq cable but it's not available so we can pull 4c×25mm sq two cables?

1405


what is the effect of un-synchronized power.

2040


What do you mean by a voltage transformer?

1144


Which Class insulation is prefered for the sandwich Busducts ? Why?

2028


what's the difference between abs/inc encoders. apart from the position remembrance what are all the other differences. and what's mean by grey code.

2078


why does the magnetic balance tests at transformer?

1939


Please help me regarding my one concern. - During earth pit testing we noticed that the Clean earth pit and dirty earth pit showing continuity (Resistance value - 5ohm) . I want to know that if both earth pit have separate location and there is not internal looping between PIT then why such continuity is showing on it . Because of this issue the field side all earthing point showing short. In PLC panel we are providing two types of earthing cable which is coming from separate earth pit (Clean and Dirty earth pit) because of earth PIT showing short our PLC is not complying spec . please help regarding this issues.

1584


WHY CBCT USE ONLY IN Y PHASE NOT OTHER PHASES

2110


what are the advantage and dis-advantage of 3 phase 4 wire energy meter?

2188


What is force on parallel conductors ?

1073


how to setting voltage RTCC panel

1665