We have a 33/11kv switchyard having 12.5 MVA power
transformer. We export & import power through this
transformer. When we export power, the PF will be depend on
GRID PF & when we import power the PF will be depend on our
load PF. but the problem is that,when neither we export nor
import but our 33KV vCB is in close position,our meter read
the power factor 0.14 to 0.25 at that moment. So how can be
we improve the power factor at that moment.
Answer Posted / k.prakashchandra
You should realise that when there is no load on
transformer, the pf is almost zero
Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
what is sevice settings for mccb?How can be it setted?
CT Ratio of a energy meter connection is Red Phase : 100/5A, yello Phase : 50/5A & Blue phase : 100/5 A what is the overall Multiplication factor
We have Diesel generator of 200KW. fuel consumption is always same,even connected light load or full load. Is it right?
how is calculated the quantity of weight in hot test xlpe?
Difference between a pilot wire and a normal conductor?
i will applied in 1U-1W on 440 volt primary delta side. what is the result of magtic balance test
What are the two basic types of transformers?
how to determine the cable size...pls explain me with the formula taking particular load....does the factors like impedance & short circuit rating influence the cable size, if so how....
Pls tell me whether we can use EN3A material for shafts of Permanent magnet alternator.What will be the effect of magnetic and nonmagnetic material for shafts on magnetic properties of PM rotor .
i want to learn control schedule for 11kv panel? can any one send the detailed control schedule?
Why are the cores of large transformers built up of circular transactions ?
what is the star delta connetion and how can do it a three phase motor with control witing with picture
For high frequency application we use which transformer?
what are the usual topology of transformers at different substations in the power system and why that particular topology is choosen. what are the limitaions of that topology?
I completed iti in2004 I was worked in A grade contractor can I get c licence