Could you please provide me a solution in Sales pricing for
the following scenario in SD Pricing.
Finished Goods Materials: A, B, C
price of A is X when sold independently.
price of A is Y when sold along with B in a sales order
price of A is Z when sold along with C in a sales order
How do you maintain pricing for the above scenario, and how
it will be is determined in sales order?
Answer Posted / rajiv trivedi
Hi Subha,
Use key field material pricing group/material attach to
access sequence-->Connect to condition type e.g. K029 Group
Condition. It will work. This is very basic in pricing
procedure. Hope you understand this procedure. If not let
me know.
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
What and where types of copy controls we change
What are the important organizational elements of sap sd?
Can items in a sales order belong to different distribution channels?
Explain what is the difference between rush order and cash sales?
What is the structure of delivery document?
Gather Information For better understanding &analyze cases received through LNOB for pirs &ccrs
What is a partner type? Give some example?
It will be really helpful if someone can provide an example / System behavior where (1) only AC is used, (2) only TOR is used, (3) both AC & TOR is used ( in schedule line category) thank you
we have a situation where i am about to design one process where only maintainence is taken care of keeping the existing product +services process intact ...Do you know how do i proceed???? where this process is a VAT free
Do you participate in implementatation? What is your role in imp. Phase? what have udone in implementation? Which methodology you use in imp.?
What is an outline agreement?
What are the basic types of information it (information structure) comprises of?
What is the structure of delivery document? What are the characteristics essential for combining more than one sales order as one outbound delivery?
What is sap transport domain? : transportation management
After setting up a batch job (schedule the backlog report) by T Code SM36, i am getting error mail from user saying that, the reports r not recieving to his mail box, can any one help me regading this, how to resolve?.....it will be greate help.. Thanks