Is there any option to replace two Genset of capacity 125KVA
with one higher capacity for same office?
Answer Posted / kpd
There are not enough details given here to give an
approriate answer.
Office back-up generators are renowned for being crammed in
to the last bit of space the facility has left. Airflows
have to be considered for cooling and also attenuation for
a larger generator is larger again causing prospective
space issues.
Economic constraints may also exist, re cabling a single
feed to the office main board in larger cable to accomodate
the single larger generator may cause issues. Also the
operating logic of any changover contactors or equipment
will massively effect the generator choice.
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What happens if the Capacitive Voltage Transformer Primary neutral is not earthed. There is a CVT between Transformer and source, and the CVT neutral of the transformer is not earthed, does it effect the transformer while charging or does it effect the transformer charging process.
Draw torque - speed curve and load curve of induction motor? mark operating point ?
Either It Possible a dc Motor to Run On Ac Drive [ Ex : ACS 800 , Yaskawa F7 ] If it is Possible How Pls Inform Me dinesh_elect_eng@yahoo.com
What is sensitivity of a measurement?
What is the best thing to protect the motor from running over full current. CT or O/L or pressure transducer at the given pressure rating
what are the main faults that occur in stabilizers? How they corrected and resolved ? Types of stabilizers ?
What is the difference between type1 and type2 relay protection co-ordination for motor feeders
What is the rating of circuit breaker needed for 300 KVA load in 33 KV supply line in a transformer of 33 KV / 415 Volt ?
can anyone show me how the 3 phase power is supplied to socket outlets?
from which subjects most of the technical que will b asked for hpcl(electrical).pls help me
what is the profesional board for electrical engineer what is thepast and during construction for electrical engineering
What is mean by hot and cold loop testing?
why we use condenser in the thermal power plant, althrough the same vapour will be again heated
What is a compensator?
How to megger test 11 kV cable and the acceptance IR value