9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement
Answer Posted / manikandan ramia sankaran
1. 9.00m x 9.00m x .15m
= 12.15 m3
12.15/(1+4+8)[x] 1.56 = 1.458m3 of cement
sand = 4 x 1.458 = 5.832 m3 of sand
4omm agg = 8 x 1.458 = 11.664 m3
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
Explain what is Hybrid Foundation?
How to calculate quanty of steel in four leg stirrups?
what r the precaution for high in atp tempareture,low in atp tempareture
In jack arch floor, the rise is kept?
Explain the difference between shear and tensile strength.
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
what are the code used for residental building?
How to find out slope footing concrete
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
What is the worlds largest concrete dam?
how many tonnes equals to one cubic feet?
What is the effect of a building collapse?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
why steel tanks are provided (a) for water pressure (b) for wind pressure (c) for earthquake pressure