Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?

Answer Posted / rajarshi basu

The approach by Sjtbehera is totally correct but has some
little silly mistakes...I have tried to give a rectified
solution.

In the case M30 design mix, the quantities of cement,sand
and aggregates cannot be calculated as it is a variable
quantity.It depends upon the Mix designer how much quantity
of cement,sand and aggregates he will employ.His only
intention would be to design a mix whose specified
characteristic compressive strength at 28 days=30 N/sq.mm
But in case of nominal mix we can use 1:1:2
Let us consider a volume of 10 cu. m (Wet concrete)

It is difficult to access exactly the amount of each
material required to produce 10 cu m of wet concrete when
deposited in place.
Hence to convert the wet volume into dry volume,
Increase by 54 % to account for shrinkage and wastage

Thus it becomes=15.4 cu. m (Variable upto 15.70)

Calculating cement, sand and aggregates in the mix:
Total summation of proportion=1+1+2=4

Cement = 15.4/4= 3.85 cu. m =3.85/0.0347=110 bags
Sand=15.4/4=3.85 cu. m
Aggregates(20mm to 6mm)=15.4 x (2/4)=7.70 cum

Hope u have understood and the mistake is clarified!!!

Is This Answer Correct ?    174 Yes 65 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

in the construction of residential building what type of tank are used?where?why & what is its purpose?

2324


How to hide dimensions in autocad?

1112


Rate analysis for construction of a solid block masonary of size 400x200x200 in C.M.1:5 in superstructure .Compressive strength 5.00 N/Sq.mm Confirming to IS: 12894:1990, with necessary scaffolding, raking of joints and pointing the same. I require rate per Cum.

2485


Why is concrete cube test carried out?

1187


can any one explain bar bending schedule of bems and columns and slabs ??

1867


i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available

1872


Who designed the city of washington dc?

1202


importance of the soundness test to determine the quality of cement use for any construction

2087


what is flashing?

1121


how to conversation of all construction material in to brass

5389


what is m30 in concrete tiles

2312


very simple or less time consuming formula for reinforcement calculation by moment

1431


Which are the top apps for you civil engineer?

1164


How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097

2199


Why are pull-out tests performed for soil nails?

1124