Answer Posted / vicky
it depends on size of block/brick
for 1 cum. of blockwork (1:6) (block size - 300X160X190mm)
you can use thumb rule i.e. 70% bricks & 30% mortar
means u have to take 30% of 1 cum. & adding 15% for wet
mortar means total 0.45 cum. mortar required, then u can
calculate the cement = 0.45/(1+6) = 0.064 cum.= 1.83 bags.
same as for brickwork
Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
what is the use of steel rods of 16mm or 20mm used for 4.45mts for closing gutter.one mate consumes how many kgs with a gap of 6inches.
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
How can you achieve soil enforcement?
What in bending moment, if a moment is free end of cantilever beam?
In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:
How to calculate canal slope curvature qty!
What is rate of concrete surface rendering work per sqm
how much of the strength comes from post-production curing
What is the strength of 1:6:12 mix?
How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?
what is Brick crushing strength(PSI)?
Gidc technical que paper
Pls provide me with the calculation or codes related to de- shuttering of flat slabs
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
How to hide dimensions in autocad?