Cement Co-eff. in block 1:6, brick1:4 work?

Answer Posted / vicky

it depends on size of block/brick
for 1 cum. of blockwork (1:6) (block size - 300X160X190mm)
you can use thumb rule i.e. 70% bricks & 30% mortar
means u have to take 30% of 1 cum. & adding 15% for wet
mortar means total 0.45 cum. mortar required, then u can
calculate the cement = 0.45/(1+6) = 0.064 cum.= 1.83 bags.

same as for brickwork

Is This Answer Correct ?    6 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the use of steel rods of 16mm or 20mm used for 4.45mts for closing gutter.one mate consumes how many kgs with a gap of 6inches.

1864


What is the life of anaerobic Digester if it is used for municipal solid waste digetion.

1801


How can you achieve soil enforcement?

630


What in bending moment, if a moment is free end of cantilever beam?

701


In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:

2942






How to calculate canal slope curvature qty!

1317


What is rate of concrete surface rendering work per sqm

1422


how much of the strength comes from post-production curing

1859


What is the strength of 1:6:12 mix?

2587


How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?

1691


what is Brick crushing strength(PSI)?

838


Gidc technical que paper

1250


Pls provide me with the calculation or codes related to de- shuttering of flat slabs

5897


asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream

1455


How to hide dimensions in autocad?

628