Answer Posted / vicky
it depends on size of block/brick
for 1 cum. of blockwork (1:6) (block size - 300X160X190mm)
you can use thumb rule i.e. 70% bricks & 30% mortar
means u have to take 30% of 1 cum. & adding 15% for wet
mortar means total 0.45 cum. mortar required, then u can
calculate the cement = 0.45/(1+6) = 0.064 cum.= 1.83 bags.
same as for brickwork
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width
how to calculate the rebar depth if forgot the foundation reinforcement (main steel)? is that any calculation or formula we have data sheet of supplier what depth what is the pull out capacity is mensioned in data sheet. if any IS code than its help full to me.
Why M15 is replaced by M20 when ammendment are made in IS456 in 2000?
What is meant by solid geometry?
what are the layers of the national and heir aprox thickness??
how many cement used in single story residential building per sqft
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
Why are separation membranes used between concrete pavement slab and sub-base?
quantity of material needed for rubble stone masonry for 1:4 and 1:6
how to calculate MR 9(derivation)
Curvature ki quantity kaise nikalte hai pls give me ans... curvature canal ka hai
Define the various stages of the project planning process in construction.
how to workable concrete cube test M-25 design mix