Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Cement Co-eff. in block 1:6, brick1:4 work?

Answer Posted / vicky

it depends on size of block/brick
for 1 cum. of blockwork (1:6) (block size - 300X160X190mm)
you can use thumb rule i.e. 70% bricks & 30% mortar
means u have to take 30% of 1 cum. & adding 15% for wet
mortar means total 0.45 cum. mortar required, then u can
calculate the cement = 0.45/(1+6) = 0.064 cum.= 1.83 bags.

same as for brickwork

Is This Answer Correct ?    6 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is a bearing capacity of soil?

1285


how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail

4061


how many re use can use shutting material. timber ? ply? steel? plastic? fibre? aluminium? Doka?

2429


Moisture content calculation for diff mix ratio's ??

1746


what is the clear cover for shearwall?

1593


in staad ,why we realease a moment of a member ? what is affect if we realease a moment

2246


what is the basic difference between Coloumn & Shear Wall

2174


what is the calculation of raw material for 0.35cum of m-15

1443


how do you calculate the quantity of steel,cement for plinth beam. (example size 41'*0.58'*1.08')

2631


what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?

2285


What are the different types of civil engineering?

1138


how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.

3757


how clculate excavated or backfilling quantity by simpson's rule

5115


Define What is the distance between railway tracks?

1111


Can a wave happen in the middle of the ocean like in the movie poseidon 2006?

1247